Design management and temporary works designers for 340m of deep-water combi-wall quay including two bespoke linkspan bankseats for an interchangeable floating linkspan. Design delivery was phased with full CAT 3 checking closely with the construction programme to ensure handover of the berth after just 183 days. Key features included:
340m deep-water combi-quay wall
Design of piles in Dublin Boulder Clays
STS crane rail (drive) piles of up to 45m long on rock
Managed design delivery utilising multiple design houses for fast track approach
Bespoke precast wall construction
Cathodic protection design
Ocean Pier, Dublin Port